Victoria Primary POC, screening decision, s37 consent, Electricity Act 1989
Screening decision to erect an H-pole, 2 poles and 2 stays associated with 33kV overhead conductors to facilitate a new ground mounted primary substation.
Applies to England
Documents
Details
To erect an H-pole, 2 poles and 2 stays associated with 33kV overhead conductors to facilitate a new ground mounted primary substation. Screening Decision 바카라 사이트“ section 37 consent, Electricity Act 1989.
Secretary of State바카라 사이트™s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of Decision
13 September 2023
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.