New wire and 3 phase transformer, Pick Wick Inn, St Issey: screening decision, s37 consent, Electricity Act 1989
Screening decision on installing third wire from pole number for 300m of overhead line, 3 phase transformer and lazy leg pole to support pole mounted transformer.
Applies to England
Documents
Details
To install a third wire from pole number for approximately 300m of overhead line, to install a three phase transformer and to erect a lazy leg pole to support a pole mounted transformer. Screening decision 바카라 사이트“ section 37 consent, Electricity Act 1989.Â
Secretary of State바카라 사이트™s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
28 June 2023
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.