James Farm overhead line, Winsor, S37 consent, Electricity Act 1989
Screening decision to upgrade 509 meters of an existing 11kV overhead line from single to 3 phase.
Applies to England
Documents
Details
Secretary of State바카라 사이트™s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
22 March 2024
Location
James Farm
Winsor
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.