Hawthorn Pit overhead line, S37 Consent, Electricity Act 1989

Screening decision to re-align a 132 kV, 304 metre overhead line to facilitate connection to a new 400 kV substation, install a new 132kV tower at a height of 46 metres and install new downleads, connecting the new tower to the substation.

Applies to England

Documents

Details

Secretary of State바카라 사이트™s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

2 August 2024

Location

Hawthorn Pit

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 2 August 2024