GLOS/41/JOH/LAWSFM4882936 overhead line, S37 Consent, Electricity Act 1989
Screening decision to upgrade approximately 592 metres of an existing 2 wire 11 kV overhead line to 3 wires, replace four poles on a like for like basis and install an H Pole to support a 200kVa pole mounted transformer.
Applies to England
Documents
Details
Secretary of State바카라 사이트™s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
14 March 2025
Location
Gloucestershire
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.