To install a 132kV pylon with cable sealing end platforms to make underground connection within existing line in close proximity to a new solar farm development. Screening Decision 바카라 사이트“ section 37 consent, Electricity Act 1989.Â
Secretary of State바카라 사이트™s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
7 July 2023
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.