Chambers Farm overhead line, S37 Consent, Electricity Act 1989
Screening decision to add a third wire to 640m of existing 11kV overhead line, replace existing transformer and wood poles, add new pole and additional stays.
Applies to England
Documents
Details
Secretary of State바카라 사이트™s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017:
- to add a third wire to 640m of existing 11kV overhead line
- replace existing transformer to support single phase to 3 phase
- replace 5 wood poles
- erect an additional pole to aid the transformer upgrade
- add 3 additional stays
Date of decision
4 December 2024
Location
Chambers Farm
Cotswolds
Gloucestershire
England
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.