Negative CO2 emissions from full scale BECCS utilising non-amine CCS chemistry

Led by C-Capture

C-Capture, the designer of world-leading and innovative chemical processes for carbon dioxide removal, alongside the Drax Group, will progress its bioenergy and carbon capture and storage (BECCS) project at Drax Power Station in North Yorkshire. It will further develop its understanding of how the technology it has developed can be scaled up, to enable Drax to become the world바카라 사이트s first negative emissions power station in the 2020s 바카라 사이트 effectively removing the greenhouse gas carbon dioxide from atmosphere at the same time as electricity is being produced.바카라 사이트The work being undertaken over the next 2 years includes:

  • an extension of C-Capture바카라 사이트s existing pilot facilities at Drax
  • plant performance and optimisation trials
  • a chemistry validation and testing programme with research partners SINTEF and the CO2 Technology Centre Mongstad (in Norway)
  • process design development to move towards commercial scale deployment, including re-purposing the existing Drax infrastructure

ACORN CCS 바카라 사이트 FEED Programme

Led by Pale Blue Dot Energy

Acorn is a full chain CCS바카라 사이트project in north east Scotland.바카라 사이트Being바카라 사이트an바카라 사이트infrastructure and storage resource led project,바카라 사이트it is specifically바카라 사이트designed to make best use of the UK바카라 사이트s built and natural assets바카라 사이트and바카라 사이트initiate CCS in the UK at바카라 사이트lowest바카라 사이트cost.바카라 사이트바카라 사이트This is achieved바카라 사이트through바카라 사이트access to바카라 사이트key바카라 사이트offshore gas pipelines that are바카라 사이트both바카라 사이트available now and suitable바카라 사이트for reuse for CO2바카라 사이트transport.바카라 사이트바카라 사이트In addition, around one third of the바카라 사이트UKCS storage resource바카라 사이트lies바카라 사이트within바카라 사이트this바카라 사이트pipeline corridor바카라 사이트including바카라 사이트access to바카라 사이트the바카라 사이트world class, well understood바카라 사이트and바카라 사이트licensed Acorn바카라 사이트CO2바카라 사이트sٴǰ바카라 사이트sٱ.바카라 사이트įAǰ CCS takes full advantage of this바카라 사이트to바카라 사이트use바카라 사이트a바카라 사이트small initial바카라 사이트inventory바카라 사이트to commission large scale CO2바카라 사이트transport and storage infrastructure that can support바카라 사이트future바카라 사이트industrial decarbonisation in바카라 사이트Scotland,바카라 사이트the바카라 사이트UK and바카라 사이트around바카라 사이트the바카라 사이트North바카라 사이트Sea Basin.바카라 사이트바카라 사이트

The BEIS CCUS funding is progressing the detailed engineering for this project towards a final investment decision in 2021.바카라 사이트

Integration of CCUS technology to a 200MW OCGT TiGRE Project located in the UK Southern North Sea

Led by TiGRE Technologies

The TiGRE Group presents potential for the lowest cost option to capture and sequester carbon. TiGRE™ is the trademark for the Transition to integrated Gas and Renewable Energy concept residing with the TiGRE Group. TiGRE™ projects under development by the TiGRE Group provide the unique opportunity to assess the feasibility of integrating conventional best-practice carbon capture and sequestration technology into a real-life production facility.

Translational Energy Research Centre (PACT-2)

Led by University of Sheffield / Pilot-Scale Advanced Capture Technology (PACT)

Funded by BEIS and European Regional Development Fund this project establishes a scale of world class research infrastructure that supports the long term competitiveness and international reputation of the UK in CCUS. The centre바카라 사이트s state-of-the-art facilities will enable UK companies to develop, de-risk, and accelerate their innovations under realistic operating conditions.바카라 사이트It will bridge the gap between fundamental research and pilot-scale demonstrations, whilst providing a training ground for the next generation of researchers.

The centre is also a channel to international collaboration through its engagement with the International Test Centre Network (ITCN), whose membership spans Norway, Canada, Australia, China, Japan and South Korea, the International Flame Research Foundation (IFRF), whose membership includes over 100 international industrial and research organisations, and the European CCS Experimental Laboratories (ECCSEL).

HyNet Phase 1: Industrial CCS

Led by Progressive Energy

HyNet is an integrated Hydrogen / CCUS project to decarbonise the North West industrial cluster. Phase 1 of this ambitious but deliverable project is to develop the CCUS infrastructure to capture CO2 emissions from industry and store them in the Liverpool Bay depleted gas fields. The HyNet project consortium of Progressive Energy, Essar Oil UK, CF Fertilisers, Peel, Cadent and the University of Chester are undertaking the 바카라 사이트pre-FEED바카라 사이트 study which will confirm technical viability of the project, mitigate engineering risks, and provide robust cost estimates for subsequent project development. HyNet will also subsequently produce hydrogen as a fuel for both heating, power and transport, and development of the hydrogen production and distribution elements of the project are being undertaken in parallel with the CCUS activities.

Clean Gas Project & Tees Valley cluster Development Select Phase

Led by OGCI Climate Investments

OGCI Climate Investments has entered into a strategic partnership with BP, ENI, Equinor, Occidental Petroleum, Shell and Total to progress the Clean Gas Project, the UK바카라 사이트s first commercial full-chain Carbon Capture Utilisation and Storage (CCUS) project in Teesside. This feasibility study is an important milestone in building the world바카라 사이트s first commercial CCUS project for a gas-fired power plant.바카라 사이트 The Clean Gas Project could form the heart of the Tees Valley CCUS Cluster that will deploy CCUS at scale.

The Clean Gas Project will use natural gas to generate power, with CO2 then captured and transported by pipeline for storage in a geological formation deep under the Southern North Sea.바카라 사이트The infrastructure created would enable industrial emitters in Teesside and elsewhere to capture and store CO2 from their processes.

The BEIS Innovation Funding will support the technical and commercial progression of the Clean Gas Project on to the next stage of development. As the project reaches this important phase, it becomes the anchor project for a decarbonised industrial cluster in Tees Valley.

Allam-Fetvedt Cycle Power Plant for UK Deployment

Led by 8 Rivers Capital, LLC

8 Rivers Capital is conducting a feasibility study for the deployment of the revolutionary Allam-Fetvedt power cycle to bring the technology to the UK. The Allam-Fetvedt cycle is a technology that achieves highly efficient and low cost electricity generation with zero emissions through use of a novel supercritical carbon dioxide as the primary process fluid. This technology has been successfully demonstrated at 50 MWth scale in La Porte, Texas, and is now being commercialised by NET Power LLC, with 8 Rivers leading development of full-scale commercial projects.

The study, conducted under the BEIS CCUS Innovation Competition, aims to achieve the primary goals of the feasibility study strand of the competition, defined as 바카라 사이트the evaluation and analysis of the potential of a project, which aims at supporting the process of decision-making by objectively and rationally uncovering its strengths and weaknesses, opportunities and threats, as well as identifying the resources required to carry it through and ultimately its prospects for success바카라 사이트.

The goal of the feasibility study will be to advance both the location-specific commercial scale design, cost and business case of a project providing 300MW of dispatchable, zero carbon electricity to the Teesside region. The feasibility study will complete a cost estimate to AACE class IV, advancing the project to the point of being ready to proceed with deployment of the full-scale system in Teesside. The program will also advance the design to reduce cost, improve reliability and investigate options for increased flexibility and grid response. 8 Rivers will be collaborating with its partners and subcontractors McDermott International, WSP and Sembcorp to successfully deliver the work.