You need a permit for most generators, furnaces and boilers.

Get a permit

The permit you need depends on the type and amount of fuel you바카라 사이트™re burning.

Part A(1) environmental permit

You바카라 사이트™ll need a Part A(1) environmental permit if your appliances:

  • have an aggregated rated thermal input of 50 megawatts (mw) or more
  • burn waste oil, recovered oil or any fuel made from waste, with a rated thermal input of 3 to 50 mw

Get a Part A(1) permit from:

Part B environmental permit

You바카라 사이트™ll need a Part B environmental permit if your appliances:

  • have a rated thermal input of 20 to 50 mw
  • burn waste excluded from the Industrial Emissions Directive (IED) with a rated thermal input of 0.4 to 3 mw

Get a Part B permit from:

  • your local council if you바카라 사이트™re in England and Wales
  • if you바카라 사이트™re in Scotland

Small Waste Incineration Plant (SWIP) environmental permit

You바카라 사이트™ll need a Small Waste Incineration Plant (SWIP) environmental permit if your appliance can burn either:

  • less than 10 tonnes per day of hazardous waste
  • less than 3 tonnes per hour of non-hazardous waste (equivalent to 72 tonnes per day)

Get a SWIP environmental permit from your local council.

Installing furnaces

Your local council must approve:

  • the use of a new non-domestic furnace in a building, fixed boiler or industrial plant
  • changes to an existing furnace

Contact your local council about getting approval for grit and dust arrestment equipment for your furnace if it바카라 사이트™s going to be used to burn:

  • pulverised fuel
  • any other solid matter at a rate of 45.4 kilograms (kg) or more an hour
  • liquid or gaseous matter at a rate equivalent to 366.4 kilowatts (kw) or more

You might not need approval if your boiler will not create emissions that can damage health or cause a nuisance. Contact your local council to check if you바카라 사이트™re exempt.

Chimney height requirements

Your chimney must be high enough to prevent smoke, grit, dust, gases and fume emissions from damaging health or causing a nuisance. Your local council can refuse your application if your chimney is not high enough.

You must apply for chimney height approval if your boiler바카라 사이트™s fuel consumption either:

  • exceeds 45.4 kg of solid fuel an hour
  • exceeds 366.4 kw of liquid or gas fuel

If your approval application is refused your local council will tell you the minimum chimney height you need.

A chimney may be exempt if it바카라 사이트™s used as part of:

  • a temporary replacement, for example if the boiler or furnace is being repaired
  • a temporary source of heat or power for building works
  • an auxiliary plant to bring the main plant up to operating temperatures
  • a mobile source of heat or power for agricultural purposes

If the use of your chimney changes you must re-apply for approval.