The 2020 EIA Regulations

The 2020 EIA Regulations

From 1st January 2021

Environmental Impact Assessments (EIA)

Projects listed in Schedule 1 of the 2020 EIA Regulations are subject to an EIA process as required by regulation 5(1). Projects listed in Schedule 2 are subject to a screening process to determine if an EIA is necessary, but the developer may wish to undertake an EIA as set out in regulation 5(2)(b), if they choose. To access further information on projects which are subject to the EIA process, please use the relevant link below.

Environmental Impact Assessments (EIA) - Transitional Cases

For projects where the Oil and Gas Authority decision on whether to grant consent is pending at the time when the 2020 EIA Regulations came into force, EIA바카라 사이트™s are subject to the provisions of regulation 29 (Transitional and Saving Provisions relating to the 1999 Regulations). To access further information on EIA projects which are subject to the provisions of regulation 29, please use the relevant link below.

Screening Directions

Projects listed in Schedule 2 of the 2020 EIA Regulations require a screening direction in accordance with regulation 5(2)(a) to determine if an EIA is necessary. Screening directions for projects which have been through the screening process since 1st January 2021 can be accessed using the link below.

Deep Drilling Screening Directions

Pipeline Screening Directions

Production Screening Directions

Regulation 5(3) Decisions that No environmental impact assessment is needed without a screening direction

Schedule 3 Projects

The 2020 EIA Regulations provide that projects that fall under Schedule 3 do not require an EIA where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7. Those projects are:

  • The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.

A list of Schedule 3 project decisions made since 1st January 2021 can be accessed at the following link:

  • (MS Excel Spreadsheet, 55.2 KB)

Updates to this page

Published 5 January 2021
Last updated 28 July 2025 show all updates
  1. Schedule 3 Projects Register - Updated

  2. Schedule 3 Projects Register

  3. Schedule 3 spreadsheet updated.

  4. Schedule 3 Projects register updated.

  5. Schedule 3 project register - updated

  6. Schedule 3 register updated

  7. Schedule 3 Projects Register - Updated

  8. Schedule 3 Projects Register updated

  9. Updated Schedule 3 Projects Register.

  10. Schedule 3 spreadsheet updated.

  11. Schedule 3 Projects Register - Uploaded

  12. Schedule 3 Projects Register updated

  13. Schedule 3 Projects Register updated

  14. Schedule 3 Project Register uploaded.

  15. Schedule 3 Spreadsheet updated.

  16. Schedule 3 Projects Register updated

  17. Schedule 3 Projects Register - Uploaded

  18. Schedule 3 Projects Register - uploaded

  19. Schedule 3 Projects Register updated

  20. Schedule 3 Spreadsheet updated.

  21. Schedule 3 Projects Register- uploaded

  22. 2025 Production Screening Directions and 2025 Pipeline Screening Directions added

  23. Schedule 3 Projects Register - uploaded

  24. Schedule 3 Projects Register updated.

  25. Schedule 3 Projects Register updated

  26. Schedule 3 register updated

  27. Uploaded Schedule 3 Projects Register w.c. 03.02.2025

  28. Schedule 3 Register updated.

  29. Schedule 3 Projects Register updated

  30. Deep Drilling Screening Directions 2025 Environmental Impact Assessments (EIA) 2025

  31. Schedule 3 Projects Register - updated

  32. Schedule 3 Projects Register updated

  33. Updated SNS Activity Tracker W/C 16/12/2024.

  34. Schedule 3 Projects Register - uploaded

  35. Schedule 3 Projects Register updated.

  36. Schedule 3 Projects Register - Uploaded

  37. Schedule 3 Projects Register- Uploaded

  38. Schedule 3 Projects Register- uploaded

  39. Schedule 3 Projects Register - file attachment updated

  40. Schedule 3 Projects Register updated

  41. Update Schedule 3

  42. Schedule 3 Spreadsheet updated.

  43. Schedule 3 Projects Register updated.

  44. Schedule 3 Projects Register updated

  45. Schedule 3 Projects Register updated

  46. Schedule 3 Projects Register updated

  47. Schedule 3 Projects register updated.

  48. Schedule 3 Projects Register updated

  49. Schedule 3 Projects Register updated

  50. Schedule 3 Tracker Update

  51. Schedule 3 Projects Register updated

  52. Schedule 3 Projects Register updated

  53. Schedule 3 Projects Register updated to most recent version

  54. Schedule 3 Projects Register updated

  55. Schedule 3 Projects Register updated

  56. Schedule 3 Projects Register updated

  57. Update Schedule 3 - 24.06.24

  58. Schedule 3 project register updated.

  59. Schedule 3 Projects Register Updated to most recent version

  60. Schedule 3 Projects Register updated

  61. Schedule 3 register updated

  62. Schedule 3 Projects Register updated

  63. Schedule 3 Projects Register updated

  64. Schedule 3 Projects Register updated to most recent version

  65. schedule 3 spreadsheet updated

  66. New link to 2024 Production Screening Directions added

  67. Schedule 3 update

  68. Schedule 3 Projects Register updated to most recent version

  69. Schedule 3 projects register updated.

  70. Update of Schedule 3 document

  71. schedule 3 project register updated to most recent version

  72. Schedule 3 Projects Register updated

  73. Schedule 3 Projects Register updated

  74. Schedule 3 Projects Register updated

  75. Schedule 3 Project Register updated

  76. Addition of link to 2024 PL screening directions

  77. Schedule 3 Projects Register updated

  78. Schedule 3 Projects Register updated to most recent version

  79. Schedule 3 - 29/01/2024

  80. 2024 page added

  81. Schedule 3 register updated

  82. Schedule 3 updated

  83. Link to Deep Drilling Screening Directions - 2024 added

  84. Schedule 3 spreadsheet updated

  85. Schedule 3 register updated

  86. Schedule 3 Projects register updated to most recent version

  87. Schedule 3 - Updated

  88. Schedule 3 updated

  89. Schedule 3 Projects Register updated

  90. Updated Schedule 3 Projects Register Spreadsheet

  91. Schedule 3 Projects Register updated to most recent version

  92. Schedule 3 projects register updated

  93. Update Schedule 3

  94. Schedule 3 Projects Register updated

  95. Schedule 3 Spreadsheet updated

  96. Schedule 3 Projects Register updated to most recent version

  97. Link added to EIA Submissions and Decisions - 2023 webpage

  98. Schedule 3 Projects Register updated to most recent version

  99. Schedule 3 Projects Register updated to most recent version

  100. Schedule 3 project register - updated

  101. Schedule 3 Projects register updated

  102. Schedule 3 Projects Register - file attachment UPDATED

  103. Schedule 3 Projects Register weekly update

  104. Schedule 3 Projects Register updated to most recent version

  105. Schedule 3 Projects register - weekly update

  106. Schedule 3 updated

  107. Schedule 3 spreadsheet updated

  108. Schedule 3 Projects register updated to most recent version

  109. Updated Schedule 3 Projects Register - 03/07/2023

  110. Schedule 3 Projects Register w.c. 26.06.2023 - updated

  111. Schedule 3 spreadsheet updated

  112. Schedule 3 Projects Register updated to most recent version

  113. Schedule 3 Project Register updated to most recent version

  114. Schedule 3 Projects Register - 29.05.2023 - UPDATE

  115. Current Schedule 3 Spreadsheet

  116. Schedule 3 Projects Register updated to most recent version

  117. Updated Schedule 3

  118. Schedule 3 Project Register updated to latest version

  119. add 2023 Pipeline Screening Directions link

  120. Schedule 3 projects register update

  121. Schedule 3 Projects Register updated

  122. Link added to Deep Drilling Screening Directions - 2023

  123. Schedule 3 Projects Register updated to most recent version

  124. Schedule 3 spreadsheet updated

  125. Schedule 3 Project Register updated.

  126. Most recent Schedule 3 projects register uploaded

  127. Schedule 3 register updated

  128. Updated Schedule 3 Projects Register added

  129. Updated Schedule 3 spreadsheet

  130. Schedule 3 Projects Register Updated

  131. Update to schedule 3 projects register

  132. Updated Schedule 3 Projects Register as at 22.08.2022

  133. Schedule 3 uploaded

  134. Schedule 3 Projects Register updated

  135. Schedule 3 register updated

  136. Schedule 3 Projects Register w.c. 18.07.2022 - Update

  137. Schedule 3 projects register updated

  138. Schedule 3 updated

  139. Schedule 3 updated

  140. Schedule 3 spreadsheet updated

  141. Schedule 3 register updated

  142. Schedule 3 updated

  143. Schedule 3 Projects Register updated to most recent version

  144. A link to 2022 Environmental Statements added.

  145. Schedule 3 updated

  146. Schedule 3 updated

  147. Schedule 3 register updated

  148. Schedule 3 replaced with the newest version

  149. Schedule 3 Register updated

  150. Schedule 3 Register updated

  151. Schedule 3 project register updated

  152. Update to Schedule 3 Projects Register

  153. Updated schedule 3 spreadsheet

  154. Addition of Pipeline Screening Directions - 2022

  155. Schedule 3 register updated

  156. Addition of link to Production Screening Direction 2022 page

  157. Weekly Schedule 3 Projects Register update

  158. Weekly Schedule 3 Projects Register Spreadsheet Update

  159. Weekly Update to Schedule 3 Projects Register

  160. Addition of Deep Drilling Screening Directions page for 2022

  161. Schedule 3 Project Tracker updated

  162. Schedule 3 tracking sheet updated.

  163. Schedule 3 tracking spreadsheet updated

  164. Schedule 3 register updated

  165. Schedule 3 tracker updated.

  166. Schedule 3 Projects Register updated.

  167. Weekly Schedule 3 Projects Register Spreadsheet

  168. Updated Schedule 3 register

  169. Schedule 3 tracking register updated.

  170. New schedule 3 register uploaded

  171. Schedule 3 Projects Register updated.

  172. Updated Schedule 3 register

  173. Updated Schedule 3 Projects Register,

  174. Schedule 3 Register updated

  175. updated schedule 3 register

  176. Weekly Schedule 3 Projects Register udpate

  177. Updated schedule 3 register

  178. Updated Schedule 3 Register

  179. Schedule 3 Projects Register weekly update

  180. Weekly Schedule 3 Projects Register update

  181. Schedule 3 projects register updated.

  182. Schedule 3 register updated

  183. Updated Schedule 3 Register

  184. Schedule 3 tracking spreadsheet updated.

  185. Updated Schedule 3 Register

  186. Schedule 3 tracker updated.

  187. Schedule 3 tracker updated.

  188. Schedule 3 register updated.

  189. Weekly 'Schedule 3 Projects Register' update

  190. Schedule 3 Register updated

  191. Schedule 3 tracking sheet updated.

  192. Schedule 3 Projects Register updated.

  193. Weekly Update to Schedule 3 Projects Register Spreadsheet

  194. Schedule 3 tracking updated.

  195. Schedule 3 tracking spreadsheet updated.

  196. Schedule 3 tracking spreadsheet updated.

  197. Update to Schedule 3 Projects Register

  198. Schedule 3 Projects Register updated.

  199. Addition of section for 'Environmental Impact Asssements (EIA) - Transitional Cases' within the 'Environmental Impact Assesssments (EIA)' section

  200. Weekly update to the Schedule 3 Projects spreadsheet

  201. Update of - Sched 3 spreadsheets - 25/01/2021

  202. 'Schedule 3 Projects Register' spreadsheet weekly update

  203. First published.

Sign up for emails or print this page