Electricity networks: transmission acceleration action plan
The government바카라 사이트™s response to the Electricity Network Commissioner바카라 사이트™s report on accelerating electricity transmission network build.
Documents
Details
The Transmission Acceleration Action Plan is the government바카라 사이트™s response to the report from Electricity Networks Commissioner Nick Winser CBE, published in August 2023.
It responds to 43 recommendations across 8 themes:
- strategic spatial planning
- design standards
- regulatory approval
- planning approval
- supply chain and skills
- communities and engagement
- outage planning
- end-to-end process and next steps
The government accepts the Commissioner바카라 사이트™s recommendations in all areas, and in some cases seeks to go further.
The Action Plan seeks to halve the end-to-end build time of electricity transmission network infrastructure, from 14 to 7 years.
We published this alongside the Electricity networks: connections action plan.